Code | Barriers | Sources | Explanations/examples |
|
B1 | Complexity of work | [65] | The higher the complexity of work, the greater the resistance to on-site LC in prefabricated buildings |
B2 | Severity of weather | [65] | Sudden gale will affect the hoisting of precast components, which is not conducive to on-site LC |
B3 | Lower prefabrication | Interview | Lower prefabrication will result in a lot of concrete pouring and steel tying |
B4 | Multilayer subcontracting | [36] | More multilayer subcontracting is not conducive to collaboration between teams in prefabricated buildings |
B5 | Poor materials | [13] | Poor materials (e.g., accuracy of precast components) will adversely affect on-site LC |
B6 | Fierce market competition environment | [45] | Too fierce market competition is not conducive to on-site LC (e.g., no time to adopt new technology) |
B7 | High turnover of workforce | [35] | The high turnover of workforce is detrimental to their conscientiousness and skills of on-site LC |
B8 | Absence of lean awareness/thinking | [38] | The absence of lean awareness is not conducive to the refined operation of precast components |
B9 | Inadequate professional skills of workers | [40] | The inadequate professional skills mean that workers lack the skills to match the on-site LC |
B10 | Inadequate professional management capability of managers | [35] | The inadequate professional management capability means that managers lack the capability to match the on-site LC |
B11 | Absence of support from senior leaders | [46] | On-site LC has not received enough attention from project managers and even the government |
B12 | Resistance to changes in LC | [46] | Due to time pressure, lack of skills, and adherence to old habits, employees are resistant to LC |
B13 | Tolerance of untidy workplaces | [35] | The 5S, an on-site LC technique, requires tidy workplaces |
B14 | Nonrecognition of LC advantages | [41] | The nonrecognition of LC advantages may bring resistance to the implementation of on-site LC |
B15 | Lack of appropriate lean technology or tools | [44] | The operation of precast components lacks corresponding lean tools |
B16 | Insufficient standardization | [42] | Prefabricated buildings are insufficient in the standardization of process, equipment, and operation |
B17 | Absence of organizational structure and culture regarding LC | [47] | The promotion and application of LC need corresponding organizational structure and culture |
B18 | Absence of relevant incentives | [34] | Since LC breaks the usual habitual practice, its promotion and application need relevant incentives |
B19 | Lack of training and education regarding LC | [37] | The installation, grouting, and caulking training of precast components are necessary for on-site LC |
B20 | Lower informatization | [4] | Informatization is conducive to the dynamic tracking of precast components |
B21 | Insufficient program planning | [48] | The insufficient program planning may cause a delay in the lifting schedule of precast components |
B22 | Lack of effective supervision and control | [49] | Lack of effective supervision and control may cause the quality problems of precast component installation |
B23 | Excessive cost savings during construction | Interview | The excessive cost savings are not conducive to the promotion and application of LC |
B24 | Insufficient funds during construction | [41] | The insufficient funds affect the sustainability of on-site construction in prefabricated buildings |
B25 | Less personal empowerment | [39] | The less personal empowerment may affect the performance of employees’ on-site LC |
B26 | Avoid making decisions and taking responsibility | [35] | Prefabricated buildings require professional teams and managers with a high sense of responsibility |
B27 | Lack of performance evaluation | [50] | The lack of performance evaluation affects the enthusiasm of employees |
B28 | Insufficient attention to green and environmental protection | [41] | The green and environmental protection is also a requirement of on-site LC in prefabricated buildings |
B29 | Lack of transparency | [38] | Transparent and accurate information is conducive to accurate decisions and actions |
B30 | Cooperation problems outside the construction department | [50] | Suppliers supply precast components on time to avoid the idleness in on-site construction |
B31 | Cooperation within the construction department | [51] | Teams compete for a tower crane during the on-site construction of prefabricated buildings |
|