Research Article

Neural Network-Based Model for Predicting Preliminary Construction Cost as Part of Cost Predicting System

Table 2

Minimal, maximal, mean value and standard deviation for the numerical variables (predictors and target).

Continuous variables
VariableRowsMinimumMaximumMeanStd. dev.

ln (planned costs, €)1169.0535818.3651113.277702.06661
ln (real costs, €)1169.0945918.5159913.358372.11371
ln (planned time, days)1162.708056.816195.070761.04090
ln (real time, days)1162.708057.509345.145281.063