Study of Deformation Behaviors and Mechanical Properties of Central Diaphragm in a Large-Span Loess Tunnel by the Upper Bench CD Method

Table 1

Construction stage of the upper bench CD method.

Excavation stageConstruction activityDiagram

IExcavate Part I, install the sidewall steel rib and central diaphragm steel rib, and construct the foot reinforcement bolt

IIExcavate Part II, install the sidewall steel rib, and construct the foot reinforcement bolt

IIIExcavate Part III and install the sidewall steel rib

IVExcavate Part IV and install the sidewall steel rib

VDismantle the central diaphragm steel rib, excavate the core soil of bottom, and install the temporary invert