Construction stage of the upper bench CD method.
| Excavation stage | Construction activity | Diagram |
| I | Excavate Part I, install the sidewall steel rib and central diaphragm steel rib, and construct the foot reinforcement bolt | |
| II | Excavate Part II, install the sidewall steel rib, and construct the foot reinforcement bolt | |
| III | Excavate Part III and install the sidewall steel rib | |
| IV | Excavate Part IV and install the sidewall steel rib | |
| V | Dismantle the central diaphragm steel rib, excavate the core soil of bottom, and install the temporary invert | |
|
|