Study of Deformation Behaviors and Mechanical Properties of Central Diaphragm in a Large-Span Loess Tunnel by the Upper Bench CD Method

Table 3

The accumulated crown settlement value at the monitoring section in Wangcun tunnel.

Pile numberPart I in the upper bench
Vault (A) (mm)Left arch waist (B) (mm)Central diaphragm waist (C) (mm)Maximum excavation line position at left arch (D) (mm)Maximum excavation line position at central diaphragm (E) (mm)

YK11 + 93713113125
YK11 + 931676054
YK11 + 9285152415845
YK11 + 9253834364613

Pile numberPart II in the upper bench
Vault (F) (mm)Right arch waist (G) (mm)Central diaphragm waist (C) (mm)Maximum excavation line position at right arch (H) (mm)Maximum excavation line position at central diaphragm (E) (mm)

YK11 + 93735534025
YK11 + 9312443606554
YK11 + 9282123413645
YK11 + 9251916361913