Dynamic Probability Analysis for Construction Schedule Using Subset Simulation
Table 2
Schedule network failure evaluation comparison.
| Part | Floors | Working segment | Duration (days/floor/segment) |
| Basement | B3∼B1 | 1, 5∼9, 21 | 30 | 2∼4, 10∼20, 22∼24 | 25 | Auxiliary building | F1∼F18 | 1, 2, 3 | 30 | Main tower | F1∼F45 | | 12 |
|
|