Dynamic Probability Analysis for Construction Schedule Using Subset Simulation
Table 3
Schedule network failure evaluation comparison (deadline = 690 days).
| Methods | Failure probability (%) | Variation coefficient | Running time (sec.) |
| MCPM | LUBE | 2.83 | N/A | 0.54 | FCPM | Triangular | 31.13 | N/A | 0.26 | PCPM | Direct MCS | 3.11 | 2.17% | 26.32 | Our method | 3.13 | 5.27% | 1.32 |
|
|