Deformation Response and Safety Evaluation of Buildings Affected by Subway-Station Construction

Table 4

Main excavated conditions of the foundation pit.

Construction stepConstruction contentExcavation depth

IInitial ground stress
IIRetaining structure construction
IIIExcavate the first layer of soil and set up the first steel support2 m
IVExcavate the second layer of soil and set up the second steel support4.5 m
VExcavate the third layer of soil and set up the third steel support4.5 m
VIExcavate the fourth layer of soil and set up the fourth steel support4.5 m
VIIExcavation to the bottom4.5 m