Research on Reasoning concerning Emergency Measures for Industrial Project Scheduling Control

Table 1

Feature attributes and value assignments for industrial project scheduling control.

No.Feature attributeValue assignment

C1Contract period 20 months = 1; > 20 months = 2
C2Contract amount 1 billion = 1; > 1 billion = 2
C3Process technologySame = 1, almost the same = 2, and similar = 3
C4Changes to contract scopeNo change = 1; change = 2
C5Changes to major design schemeNo change = 1; change = 2
C6Delay of key equipment 1 month = 1; > 1 month = 2
C7Change in construction schemeNo change = 1, minor change = 2, large change = 3, and significant change = 4
C8Allocation of direct construction labor 1000 people = 1; > 1000 people = 2
C9Schedule impact of safety accidentsNo safety accident = 1, minor safety accident = 2, major safety accident = 3, serious safety accident = 4, and severe safety accident = 5
C10Schedule impact of quality accidentsNo quality accident = 1, minor quality accident = 2, major quality accident = 3, serious quality accident = 4, and severe quality accident = 5
C11Scope of total time deviation 1 month = 1; > 1 month = 2
C12Node type affected by schedule node deviationProject-level node = 1, department-level node = 2, and company-level node = 3