Investigation on the Influence Caused by Shield Tunneling: WSN Monitoring and Numerical Simulation

Table 2

Monitoring scheme of shield construction affected area.

Monitoring objectMonitored parametersLayout scheme of monitoring pointsMeasurement points

Adjacent buildingsTilting(1) The monitoring range is the buildings within 30 meters from the central line of the tunnel4
(2) The building displacement monitoring points are arranged on the external wall or bearing column
(3) The distance between monitoring points along the external wall should be 10 m ∼ 15 m
(4) The intelligent terminal is arranged within the visual range of 100 meters of the inclination fulcrum

Shield segmentClearance convergence(1) The measuring points in the building area are arranged one for every 8 rings21
(2) The measuring points of other sections are arranged one for every 20 rings
(3) One relay jump fulcrum is set every 90 meters (13 fulcrums in total), and the intelligent terminal is arranged in the tunnel starting shaft