Optimization of Flow Shop Scheduling in Precast Concrete Component Production via Mixed-Integer Linear Programming

Table 1

Operation time and weight value of the six components in each process.

Component numberProcess operation time (h)Delivery period (h)Weight value (unit/h)
Mold assemblingReinforcement settingConcrete castingMold removalFinishing/repairingRestoring timeDelay time

110.81.21.50.528210
21.7221.52.528210
30.40.50.60.5028110
40.30.40.50.4128110
51.51.81.21.51.552210
61.51.61.51.80.832210