Optimization of Flow Shop Scheduling in Precast Concrete Component Production via Mixed-Integer Linear Programming

Table 3

Completion time of each process based on MILP.

Component production sequenceProcess completion time (h)Delay time (h)Restoring time (h)
Mold assemblingReinforcement settingConcrete castingCuringMold removalFinishing/repairing

40.30.71.22424.425.42.6
22462425.928.40.4
32.44.56.62426.428.40.4
13.45.37.82427.928.90.9
64.96.99.32429.730.51.5
56.424.725.94849.5511
Total delay time (h)1.7
Total restoring time (h)5.1

Orders complete time.