Optimization of Flow Shop Scheduling in Precast Concrete Component Production via Mixed-Integer Linear Programming

Table 6

Overtime plan for scheme (1).

Component production sequenceProcess operation time (h)
Mold assemblingReinforcement settingConcrete castingMold removalFinishing/repairing

100000
200000
300000
400000
500100
6012.500.8
701.83.70.70
800000
900000
1000000
Overtime of each process (h)02.87.20.70.8
Total overtime (h)11.5