Optimization of Flow Shop Scheduling in Precast Concrete Component Production via Mixed-Integer Linear Programming

Table 8

Completion time of each process for scheme (2).

Component production sequenceProcess completion time (h)
Mold assemblingReinforcement settingConcrete castingCuringMold removalFinishing/repairing

330.40.91.52424.5
440.71.322424.9
222.44.46.42426.4
553.96.27.62427.9
114.978.82429.4
666.48.610.32431.2
777.49.411.52432.7
8825.127.129.14849.5
9925.427.529.64849.9
101026.929.330.84851.4