Risk judgment matrix of foundation pit construction.
| ā | Judgment matrix of risk events in foundation pit construction | | | Risk index | Total risk index | A | B | C | D | E | F | G | H |
| A | 1 | 1/3 | 1/5 | 1/7 | 1/3 | 1/5 | 3 | 3 | 0.52 | 5.7% | 6.00 | 6.9 | B | 3 | 1 | 1/3 | 1/7 | 3 | 5 | 1/4 | 1/3 | 0.81 | 8.8% | 6.53 | C | 5 | 3 | 1 | 1/5 | 1/2 | 1/2 | 3 | 7 | 1.41 | 15.4% | 6.12 | D | 7 | 7 | 5 | 1 | 1/3 | 1/2 | 7 | 7 | 2.59 | 28.2% | 7.20 | E | 3 | 1/3 | 2 | 3 | 1 | 1/4 | 5 | 5 | 1.57 | 17.1% | 7.70 | F | 5 | 1/5 | 2 | 2 | 4 | 1 | 1/5 | 1/5 | 0.95 | 10.3% | 6.70 | G | 3 | 4 | 1/3 | 1/7 | 1/5 | 5 | 1 | 1/7 | 0.73 | 8.0% | 6.67 | H | 1/3 | 1/3 | 1/7 | 1/7 | 1/5 | 5 | 7 | 1 | 0.60 | 6.5% | 6.90 |
|
|