Identification and Assessment of Subway Construction Risk: An Integration of AHP and Experts Grading Method
Table 33
Risk judgment matrix of station structure construction.
| ā | Risk judgment matrix of station structure construction | | | Risk index | Total risk index | A | B | C | D | E |
| A | 1 | 1/2 | 1/3 | 1 | 3 | 0.870550563 | 14.34% | 6.39 | 6.5 | B | 2 | 1 | 1/2 | 2 | 4 | 1.515716567 | 24.97% | 6.59 | C | 3 | 2 | 1 | 3 | 5 | 2.459509486 | 40.52% | 6.6 | D | 1 | 1/2 | 1/3 | 1 | 3 | 0.870550563 | 14.34% | 6.44 | E | 1/3 | 1/4 | 1/5 | 1/3 | 1 | 0.35395292 | 5.83% | 6 |
|
|