Identification and Assessment of Subway Construction Risk: An Integration of AHP and Experts Grading Method

Table 7

Schedule delay grade standard.

LevelABCDE

Long-term projectThe delay is greater than 9 monthsDelays range from 6 to 9 monthsDelays range from 3 to 6 monthsDelays range from 1 to 3 monthsDelay of less than one month
Short-term projectThe delay is greater than 90 dThe delay is greater than 60∼90 dThe delay is greater than 30∼60 dThe delay is greater than 10∼30 dThe delay is less than 10 d