Research Article

Suspender Replacement Method for Long-Span Concrete-Filled Steel Tubular Arch Bridges and Cable Force Measurement Based on Frequency Method

Table 5

Conversion relationship between old suspender cable force and temporary suspender during unloading.

Step no.Cable force of old suspender (%)Temporary suspender 1 (%)Temporary suspender 2 (%)Temporary suspender 3 (%)Temporary suspender 4 (%)

11000000
2902.52.52.52.5
36010101010
43017.517.517.517.5
5025252525