Suspender Replacement Method for Long-Span Concrete-Filled Steel Tubular Arch Bridges and Cable Force Measurement Based on Frequency Method

Table 6

Conversion relationship between new suspender cable force and temporary suspender under loading.

Step no.Cable force of old suspender (%)Temporary suspender 1 (%)Temporary suspender 2 (%)Temporary suspender 3 (%)Temporary suspender 4 (%)

1025252525
21022.522.522.522.5
34015151515
4707.57.57.57.5
51000000