Research Article
Case Study on BIM and Value Engineering Integration for Construction Cost Control
Table 10
Value coefficient calculation table of the CJ building construction project.
| Components | Elements | Function coefficient (F) | Cost (ten thousand RMB) | Cost factor (C) | Value coefficient (c) | Need improvement |
| Structural works (A1) | A11 | 0.2957 | 3895.64 | 0.2994 | 0.9876 | ✓ | A12 | 0.0677 | 1823.02 | 0.1401 | 0.4832 | ✓ | A13 | 0.0259 | 1041.38 | 0.0800 | 0.3236 | ✓ | A14 | 0.0178 | 1006.42 | 0.0774 | 0.2301 | ✓ |
| Services and installation works (A2) | A21 | 0.1892 | 1794.71 | 0.1379 | 1.5579 | — | A22 | 0.0883 | 250.68 | 0.0193 | 3.2802 | — | A23 | 0.0209 | 129.78 | 0.0100 | 1.6542 | — |
| Finishes’ works (A3) | A31 | 0.2149 | 1568.2 | 0.1205 | 1.5697 | — | A32 | 0.0632 | 1294.74 | 0.0995 | 0.8863 | ✓ | A33 | 0.0165 | 206.37 | 0.0159 | 1.3177 | — |
| All combined | | 1 | 13010.94 | 1 | | |
|
|