Case Study on BIM and Value Engineering Integration for Construction Cost Control

Table 3

Cost of components and elements of the CJ building in ten thousand RMB (USD).

Building componentsName of elementAbbreviation of elementsCost of elementCost of componentsPercentage of cost (%)

Structural (A1)Steel and concrete worksA113895.64 (573.36)7766.46 (1143.07)55
Basement and underground worksA121823.02 (268.31)
Masonry worksA131041.38 (153.27)
Floor workA141006.42 (148.12)

Services and installations (A2)Hydropower, HVAC, and fire protectionA211794.71 (264.15)3069.31 (451.74)21.8
Elevator worksA22250.68 (36.90)
Doors and windowsA23129.78 (19.10)

Finishes (A3)Wall decoration worksA311568.2 (230.81)2175.17 (320.14)15.4
Coating insulation worksA321294.74 (190.56)
Ceiling decoration worksA33206.37 (30.37)

Others1100.01 (161.90)1100.01 (161.90)7.8

Total14110.95 (2049.22)100