Case Study on BIM and Value Engineering Integration for Construction Cost Control
Table 4
Judgment matrix (A) and weight calculation of the CJ building construction project.
| CJ building project A | Structural works A1 | Services and installation works A2 | Finishes’ works A3 | Weight Wi |
| Structural works A1 | 1 | 7 | 8 | 0.7766 | Services and installation works A2 | 1/7 | 1 | 3 | 0.1530 | Finishes works A3 | 1/8 | 1/3 | 1 | 0.0704 | |
|
|