Case Study on BIM and Value Engineering Integration for Construction Cost Control

Table 9

Comprehensive weight calculation results.

IndicatorsSubjective weight WObjective weight Comprehensive weights T

Steel and concrete A110.67050.14250.2957
Underground basement A120.17240.12690.0677
Masonry works A130.09350.08940.0259
Floor works A140.06360.09040.0178
Water, HVAC, and fire protection A210.63480.09630.1892
Elevator works A220.28720.09930.0882
Doors and windows A230.07800.08670.0209
Wall decoration A310.69860.09940.2149
Coating insulation A320.23700.08610.0632
Ceiling decoration A330.06430.08300.0165