A DSM-Based CCPM-MPL Representation Method for Project Scheduling under Rework Scenarios

Table 3

Case activity parameters.

IDActivityDuration (day)Learning curve
OptimisticMost likelyPessimistic

APerform preliminary market analysis58150.5
BEvaluate marketability options58150.6
CEngage feasibility consultants3470.3
DEvaluate planning and zoning process1013200.5
EPerform massing study2024350.6
FDevelop conceptual design3035500.8
GIdentify external stakeholders58150.4
HIdentify permits and approvals1013200.7
IComplete phase 1 ESA1013200.3
JEvaluate consultants and contractors1013200.6
KObtain rough construction costs58150.5
LDetermine highest and best use3590.5
MIdentify debt options2480.4
NIdentify equity options3450.5
OUpdate financial underwriting1230.5
PReevaluate the organization strategy2350.6
QEstimate the schedule3470.6
RGain control of the site and/or client3470.6
SReview and approve3470.7