A DSM-Based CCPM-MPL Representation Method for Project Scheduling under Rework Scenarios
| | Project buffer (day) | Project duration (day) | Buffer consuming rate on average (%) | On-time completion probability (%) |
| The proposed method | 40.03 | 108.70 | 89.39 | 85.40 | Zhang’s method | 35.58 | 104.25 | 100.57 | 50.40 | Original RSEM | 33.43 | 102.11 | 107.04 | 34.60 |
|
|