A DSM-Based CCPM-MPL Representation Method for Project Scheduling under Rework Scenarios

Table 4

Case project results.

Project buffer (day)Project duration (day)Buffer consuming rate on average (%)On-time completion probability (%)

The proposed method40.03108.7089.3985.40
Zhang’s method35.58104.25100.5750.40
Original RSEM33.43102.11107.0434.60