A Dynamic Just-in-Time Component Delivery Framework for Off-Site Construction

Table 2

Sample incentives and surcharges for delayed delivery.

Components1 d ($)2 d ($)3 d ($)4 d ($)5 d ($)6 d ($)7 d ($)

C01100200300000−100
C0210000200400600−800
C03300−60030006009001,200
C0440080004008001,200−1,600
C055001,000150001,0001,5002,000
C06−100−20006001,2000200
C07−100−200300100200300400