A Dynamic Just-in-Time Component Delivery Framework for Off-Site Construction

Table 3

Component delivery delays and surcharges/incentives.

ComponentsVolume (m3)Delay for assembly (day)Surcharges/incentives for the delivery delays
1 d ($)2 d ($)3 d ($)4 d ($)5 d ($)6 d ($)7 d ($)

C011071002003000000
C02207−10000200400600800
C0330730060090006009001,200
C0440340080004008001,2001,600
C055075001,0001,5000−2001,5002,000
C066076001,20006001,20000
C07105100200300100200300400
C08207200400600200400600800
C093073006009000−1009001,200
C104074008001,2004008001,2001,600
C115075001,0000−2001,0001,5002,000
C126073000−2006001,2001,8002,400
C13107100200300100200300400
C14207200400600200400600800
C153073006000−2006009001,200
C164074008001,2004008001,2001,600
C175075001,0001,5005001,0001,5002,000
C186076001,2001,8006001,2001,8002,400
C19107100200300100200300400
C20207200400600200400600800

The underlined negative numbers represent incentives.