A Dynamic Just-in-Time Component Delivery Framework for Off-Site Construction

Table 4

Surcharge and incentive for optimised delivery delay of components.

ComponentsVolume (m3)Delay for assembly (day)Optimised delivery delay (day)Surcharge/incentive ($)Inventory cost ($)Double handling cost ($)

C011077000
C02207780000
C033074090020
C04403001,20020
C055075āˆ’2001,00020
C066077000
C07105520000
C08207780000
C0930771,20000
C1040771,60000
C1150772,00000
C1260772,40000
C13107740000
C14207780000
C1530771,20000
C1640771,60000
C1750772,00000
C1860772,40000
C19107740000
C20207780000