A Dynamic Just-in-Time Component Delivery Framework for Off-Site Construction
Table 4
Surcharge and incentive for optimised delivery delay of components.
| Components | Volume (m3) | Delay for assembly (day) | Optimised delivery delay (day) | Surcharge/incentive ($) | Inventory cost ($) | Double handling cost ($) |
| C01 | 10 | 7 | 7 | 0 | 0 | 0 | C02 | 20 | 7 | 7 | 800 | 0 | 0 | C03 | 30 | 7 | 4 | 0 | 900 | 20 | C04 | 40 | 3 | 0 | 0 | 1,200 | 20 | C05 | 50 | 7 | 5 | ā200 | 1,000 | 20 | C06 | 60 | 7 | 7 | 0 | 0 | 0 | C07 | 10 | 5 | 5 | 200 | 0 | 0 | C08 | 20 | 7 | 7 | 800 | 0 | 0 | C09 | 30 | 7 | 7 | 1,200 | 0 | 0 | C10 | 40 | 7 | 7 | 1,600 | 0 | 0 | C11 | 50 | 7 | 7 | 2,000 | 0 | 0 | C12 | 60 | 7 | 7 | 2,400 | 0 | 0 | C13 | 10 | 7 | 7 | 400 | 0 | 0 | C14 | 20 | 7 | 7 | 800 | 0 | 0 | C15 | 30 | 7 | 7 | 1,200 | 0 | 0 | C16 | 40 | 7 | 7 | 1,600 | 0 | 0 | C17 | 50 | 7 | 7 | 2,000 | 0 | 0 | C18 | 60 | 7 | 7 | 2,400 | 0 | 0 | C19 | 10 | 7 | 7 | 400 | 0 | 0 | C20 | 20 | 7 | 7 | 800 | 0 | 0 |
|
|