A Dynamic Just-in-Time Component Delivery Framework for Off-Site Construction

Table 6

Result with the “end” activity’s delay tolerance being 3 days.

ComponentC01C02C03C04C05C06C07C08C09C10C11C12C13C14C15C16C17C18C19C20End

Scheduled348611141216171802468101216182022
Revised34813111714191919146810121418202325
Actual delay (day)000703232112222222233
Revenue ($)000160000200−600200−100100200200200−300200200200100−6000

The revenue is calculated with the actual delay.