Comprehensive Framework of Major Power Project Management Based on System Thinking

Table 1

Comprehensive evaluation indicators and weights of major power project management.

DimensionLayerWeight of layerIndicatorWeight of indicatorIntegrated weight

Construction entityProject breakdown structure (A)0.0728EBS (a1)0.50000.0364
WBS (a2)0.50000.0364

Objective managementQuality management (B)0.1510Quality management system (b1)0.39560.0597
Physical quality (b2)0.27470.0415
Quality behavior (b3)0.32970.0498
Safety management (C)0.1510Safety management system (c1)0.26830.0405
Risk control (c2)0.18630.0281
Hazard elimination (c3)0.22350.0338
Accidents, injuries and deaths (c4)0.32190.0486
Schedule management (D)0.1258Schedule management system (d1)0.24790.0312
Milestone control (d2)0.24790.0312
Acceleration measurements (d3)0.20660.0260
Construction delay (d4)0.29750.0374
Cost management (E)0.1049Cost management system (e1)0.25860.0271
Payment control (e2)0.21550.0226
Cost saving measurements (e3)0.21550.0226
Cost overrun (e4)0.31030.0325
Environment protection (F)0.0874Environment protection system (f1)0.39560.0346
On-site environment protection (f2)0.32970.0288
Green construction (f3)0.27470.0240

OrganizationOrganization and coordination (G)0.1812OBS ()0.28350.0514
Responsibility mechanism ()0.23620.0428
Coordination mechanism ()0.19690.0357
Political mechanism ()0.28350.0514

Technical supportTechnical support (H)ā€‰New technology utilization (h1)0.25460.0320
Intelligent construction site (h2)0.21220.0267
Information technology (h3)0.17680.0222
Innovation and promotion (h4)0.35640.0449