Mixed Production Line Optimization of Industrialized Building Based on Ant Colony Optimization Algorithm

Table 1

The work content of the specific process.

ProcessActivityDescription of activity content

1Mould cleaningClean the contaminants remaining in the steel film, and clean the mold table, the mold is sprayed with isolating paint
2Die installationInstall the mould of the production component
3Steel skeleton and mesh installationPlace the steel skeleton in the mould for positioning and binding the mesh
4Preinstalled embedded partsInstallation and fixing of embedded parts
5Professional inspectionConfirm that the dimensions and positions of molds, embedded parts, holes, etc. are correct
6Concrete pouringPour the concrete according to the production plan and fully vibrate it
7Maintenance componentsAccording to the requirements of components and construction period, adopt different maintenance strategies
8Components demoulding and liftingStrictly follow the order of technical disclosure requirements to demould and lift
9Stacking and storageStack finished components that meet the strength requirements in the storage area