Hardening parameters of the grout.

Hardening parameters of the groutSimulation step 2Simulation step 3Simulation step 4Simulation step 5Simulation step 6
Off ring for 0∼8 hOff ring for 8∼16 hOff ring for 16∼24 hOff ring for 1∼7 dOff ring for 7∼28 d

E/MPa51530100200
λ0.450.420.370.320.24