Experimental Study on Stability of Long-Span PC Cable-Stayed Bridge during the Construction Periods
| Experimental conditions | Load cases | Load configuration |
| The first load | 100% times loading | The tower has a weight of 510 kg. The main beam is loaded with a total of 455 kg | The second load | Midspan + hanging basket | At the end of the midspan, a weight of 5.7 kg is used to simulate the hanging basket, when the main beam is asymmetrical | The third load | Midspan + hanging basket side span + hanging basket + closure segment | A 10.7 kg weight is added to the end of the side to simulate the hanging basket and the closing section | The fourth load | 200% times loading | Remove the load applied for the second and third times and then load 500 kg symmetrically on the main beam | The fifth load | 300% times loading | Load 500 kg symmetrically on the main beam | The sixth load | 400% times loading | Load 500 kg symmetrically on the main beam |
|
|