Research Article

Study on Complexity of Precast Concrete Components and Its Influence on Production Efficiency

Table 12

Ranking for the influence weights of the complexity indices on production efficiency.

First-level complexity indices (latent variable)Second-order path coefficient PiWeight of first-level indices QiSecond-level complexity indices (observed variables)First-order path coefficient Pi,jWeight of second-level indices Qi,jRanking of Qi,jTotal weights, QjRanking of Qj

Structural complexity D1−0.540.321Surface-to-volume ratio F110.760.19440.0627
Number of openings F120.660.16850.05416
Reinforcement ratio F130.760.19430.0628
The number of embedded parts F140.820.20920.0674
Amount of exposed rebar F150.920.23510.0761

Production complexity D2−0.530.316Material consumption F210.790.20520.0656
Mold assembly time F220.750.19530.0619
Mold manufacturing accuracy F230.720.18740.05910
Waiting time in production line F240.880.22910.0722
Abnormal production status F250.710.18450.05811

Management complexity D3−0.610.363Operating proficiency of workers F310.840.17820.0655
Mold turnover rate F320.730.15560.05615
Delivery delay F330.750.15950.05812
Repair rate F340.760.16130.05813
Degree of automation of production line F350.890.18810.0693
Information management level F360.750.15940.05814