Closure Scheme Analysis of 3 × 70 m Bearingless Integral Rigid Frame Bridge of Fuzhou Xiamen High-Speed Railway
Table 7
Each closure scheme considers/does not consider the maximum stress (MPa) of the main beam and pier under the action of temperature.
| Closure schemes | Maximum span number in the closure process | Considering the effect of temperature | Not considering the effect of temperature | Bridge pier | Main beam | Bridge pier | Main beam |
| Scheme 1 | 7 | 6.1 (1.0) | 3.6 (1.3) | 2.8 | 1.3 | Scheme 2 | 5 | 3.1 (0.9) | 2.3 (0.6) | 1.2 | 1.3 | Scheme 3 | 7 | 6.1 (1.0) | 3.6 (1.3) | 2.7 | 1.3 | Scheme 4 | 3 | 4.3 (2.6) | 1.4 (1.3) | 2.6 | 1.3 | Scheme 5 | 7 | 6.5 (1.0) | 3.9 (1.3) | 2.8 | 1.3 | Scheme 6 | 5 | 3 (0.9) | 2.5 (0.6) | 1.2 | 1.3 | Scheme 7 | 7 | 6.6 (1.0) | 3.9 (1.3) | 2.7 | 1.3 | Scheme 8 | 3 | 4.6 (2.7) | 1.4 (1.3) | 2.7 | 1.3 |
|
|
Note. The values in brackets refer to the structural stress at the corresponding position without considering temperature load.
|