Research Article
Optimization in Construction Management Using Adaptive Opposition Slime Mould Algorithm
Table 1
Specific activities method of case 1.
| ID | Activities | Successors |
| 1 | Site clearance | 2 | 2 | Excavation | 3 | 3 | Footing | 4 | 4 | Formwork | 5 | 5 | Retaining wall | 6 | 6 | Basement | 7 | 7 | Slab | 8 | 8 | Exterior wall | 9 | 9 | Interior wall | 13 | 10 | Flooring | — | 11 | Exterior finish | — | 12 | Interior finish | — | 13 | Roof | 10, 11, 12 |
|
|