Schedule of construction phases of Zone 1–Zone 3.

ZonesDescriptionStart date (day from 2019/3/26)End date (day from 2019/3/26)Stage

Zone 1Excavate to Level 1 (−5.0 m)2020/06/12 (Day 444)2020/07/02 (Day 464)Stage 1
Construct 1st strut2020/07/07 (Day 469)2021/01/09 (Day 655)Stage 2
Excavate to Level 2 (−10.0 m)2021/01/15 (Day 661)2021/03/16 (Day 721)Stage 3
Construct 2nd strut2021/03/24 (Day 729)2021/04/10 (Day 746)Stage 4
Excavate to Level 3 (−15.9 m)2021/04/13 (Day 749)2021/06/30 (Day 827)Stage 5
Finish the base plate2021/07/01 (Day 828)2022/05/08 (Day 1,139)Stage 6

Zone 2Excavate to Level 1 (−5.0 m)2020/06/12 (Day 444)2020/07/02 (Day 464)Stage 1
Construct 1st strut2020/07/07 (Day 469)2021/01/09 (Day 655)Stage 2
Excavate to Level 2 (−10.0 m)2021/01/21 (Day 667)2021/02/26 (Day 703)Stage 3
Construct 2nd strut2021/02/28 (Day 705)2021/03/19 (Day 724)Stage 4
Excavate to Level 3 (−16.5 m)2021/03/28 (Day 733)2021/04/13 (Day 749)Stage 5
Construct 3rd strut2021/04/20 (Day 756)2021/07/15 (Day 842)Stage 6
Excavate to Level 4 (−24.56 m)2021/07/24 (Day 851)2022/02/11 (Day 1,053)Stage 7

Zone 3Excavate to Level 1 (−5.0 m)2020/06/12 (Day 444)2020/07/02 (Day 464)Stage 1
Construct 1st strut2020/07/07 (Day 469)2020/11/20 (Day 605)Stage 2
Excavate to Level 2 (−10.0 m)2020/12/04 (Day 619)2020/12/09 (Day 624)Stage 3
Construct 2nd strut2020/12/10 (Day 625)2020/12/18 (Day633)Stage 4
Excavate to Level 3 (−16.5 m)2020/12/20 (Day 635)2021/01/10 (Day 656)Stage 5
Construct 3rd strut2021/01/13 (Day 659)2021/02/02 (Day 679)Stage 6
Excavate to Level 4 (−20.45 m)2021/03/16 (Day 721)2021/04/22 (Day 758)Stage 7
Construct 4th strut2021/07/18 (Day 845)2021/09/02 (Day 891)Stage 8
Excavate to Level 5 (−34.68 m)2021/11/01 (Day 951)2022/05/08 (Day 1,139)Stage 9