Estimation of Costs and Durations of Construction of Urban Roads Using ANN and SVM
Table 2
Number of projects according to the offered number of days for realisation.
| Number | Offered number of days | Number of projects | Percentage share in the data base [%] |
| (1) | Up to 20 | 50 | 30.12 | (2) | 21 to 30 | 31 | 18.67 | (3) | 31 to 40 | 24 | 14.46 | (4) | 41 to 50 | 26 | 15.66 | (5) | 51 to 60 | 14 | 8.43 | (6) | 61 to 70 | 5 | 3.01 | (7) | 71 to 80 | 7 | 4.22 | (8) | 81 to 90 | 4 | 2.41 | (9) | Above 90 | 5 | 3.01 |
|
|