Estimation of Costs and Durations of Construction of Urban Roads Using ANN and SVM
Table 7
ANN models (min-max).
| Model | Network | Activation function hidden neurons | Activation function output neurons | MAPE training (cost) [%] | MAPE training (duration) [%] | MAPE testing (cost) [%] | MAPE testing (duration) [%] |
| ANN 1 | MLP 12-4-2 | Tanh | Identity | 42.79 | 31.85 | 40.54 | 35.48 | ANN 2 | MLP 11-6-2 | Logistic | Identity | 41.88 | 31.82 | 26.97 | 30.22 | ANN 3 | MLP 12-6-1 | Tanh | Identity | 33.02 | / | 25.38 | / | ANN 4 | MLP 11-7-1 | Tanh | Identity | 39.16 | / | 26.88 | / | ANN 5 | MLP 12-8-1 | Tanh | Identity | / | 34.16 | / | 26.26 | ANN 6 | MLP 11-10-1 | Logistic | Identity | / | 33.29 | / | 35.16 |
|
|