Research Article
The Portfolio Balanced Risk Index Model and Analysis of Examples of Large-Scale Infrastructure Project
Table 9
Single risk factor parameter and coefficient of the HZMB in initial construction stage.
| Stages | Sequence | Risk factor | Probability coefficient | Objective severity coefficient | Subjective feeling coefficient | Single risk factor parameter |
| Initial construction stage | 1 | Risk of being poorly designed (R11) | 0.43 | 0.73 | 1.14 | 0.36 | 2 | Innovation risk (R12) | 0.50 | 0.70 | 1.02 | 0.36 | 3 | Risk of nontimely funding(R21) | 0.42 | 0.83 | 1.22 | 0.43 | 4 | The risk of rising costs (R22) | 0.64 | 0.65 | 0.92 | 0.38 | 5 | The risk of regional system differences (R31) | 0.56 | 0.47 | 0.82 | 0.22 | 6 | The public against risks (R32) | 0.31 | 0.74 | 1.33 | 0.31 | 7 | Typhoon risk (R41) | 0.69 | 0.81 | 1.29 | 0.72 | 8 | Earthquake risk (R42) | 0.21 | 0.95 | 1.56 | 0.31 | 9 | Chloride salt corrosion risk (R43) | 0.54 | 0.65 | 1.03 | 0.36 | 10 | Schedule control risk (R51) | 0.58 | 0.55 | 0.97 | 0.31 | 11 | Quality management risk (R52) | 0.37 | 0.90 | 1.44 | 0.48 | 12 | Safety management risk (R53) | 0.41 | 0.83 | 1.36 | 0.46 | 13 | Legal conflict or blind area risk (R61) | 0.42 | 0.71 | 1.05 | 0.31 |
|
|