The Portfolio Balanced Risk Index Model and Analysis of Examples of Large-Scale Infrastructure Project

Table 9

Single risk factor parameter and coefficient of the HZMB in initial construction stage.

StagesSequenceRisk factorProbability coefficientObjective severity coefficientSubjective feeling coefficientSingle risk factor parameter

Initial construction stage1Risk of being poorly designed (R11)0.430.731.140.36
2Innovation risk (R12)0.500.701.020.36
3Risk of nontimely funding(R21)0.420.831.220.43
4The risk of rising costs (R22)0.640.650.920.38
5The risk of regional system differences (R31)0.560.470.820.22
6The public against risks (R32)0.310.741.330.31
7Typhoon risk (R41)0.690.811.290.72
8Earthquake risk (R42)0.210.951.560.31
9Chloride salt corrosion risk (R43)0.540.651.030.36
10Schedule control risk (R51)0.580.550.970.31
11Quality management risk (R52)0.370.901.440.48
12Safety management risk (R53)0.410.831.360.46
13Legal conflict or blind area risk (R61)0.420.711.050.31