Measuring the Project Management Complexity: The Case of Information Technology Projects
Table 3
Complexity groups, importance in IT projects.
| | 1 | 2 | 3 | 4 | 5 | Average | Total Responses |
| Objectives, Requirements, Expectations | 3 8.11% | 2 5.41% | 2 5.41% | 5 13.51% | 25 67.57% | 4.27 | 37 | Interested Parties, Integration | 1 2.70% | 1 2.70% | 7 18.92% | 12 32.43% | 16 43.24% | 4.11 | 37 | Cultural and social context | 3 8.11% | 3 8.11% | 22 59.46% | 8 21.62% | 1 2.70% | 3.03 | 37 | Degree of innovation, general conditions | 1 2.70% | 5 13.51% | 12 32.43% | 15 40.54% | 4 10.81% | 3.43 | 37 | Project structure, demand for coordination | 3 8.11% | 3 8.11% | 7 18.92% | 19 51.35% | 5 13.51% | 3.54 | 37 | Project organisation | 4 10.81% | 3 8.11% | 5 13.51% | 14 37.84% | 11 29.73% | 3.68 | 37 | Leadership, teamwork, decisions | 3 8.11% | 3 8.11% | 3 8.11% | 15 40.54% | 13 35.14% | 3.86 | 37 | Resources incl. finance | 2 5.41% | 3 8.11% | 12 32.43% | 9 24.32% | 11 29.73% | 3.65 | 37 | Risk and opportunities | 1 2.70% | 2 5.41% | 9 24.32% | 17 45.95% | 8 21.62% | 3.78 | 37 | PM methods, tools and techniques | 3 8.11% | 6 16.22% | 12 32.43% | 10 27.03% | 6 16.22% | 3.27 | 37 | Technology | 2 5.41% | 6 16.22% | 13 35.14% | 9 24.32% | 7 18.92% | 3.35 | 37 |
|
|