Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast
Table 2
Characteristics of the schedules for the projects under analysis.
Hydroelectric project
Total tasks
Summary tasks
Scheduled duration
Planned cost
months
million US$
Santiago
797
29
68
2684
Cardenillo
120
37
75
944
Mazar Dudas
1306
29
27
56
Sopladora
562
29
47
678