Outcome of simulation models for total duration.
| Hydroelectric | Schedule at Completion | Duration probability equal to or | Estimated duration for | project | 95% probability | (SAC) | less than SAC | months | | months |
| Santiago | 68 | 6.8 | 78 | Cardenillo | 75 | 4.2 | 83 | Mazar Dudas | 27 | 7.9 | 32 | Sopladora | 47 | 14.1 | 55 |
|
|