Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast

Table 3

Outcome of simulation models for total duration.

HydroelectricSchedule at CompletionDuration probability equal to orEstimated duration for
project95% probability
(SAC)less than SAC
monthsmonths

Santiago686.878
Cardenillo754.283
Mazar Dudas277.932
Sopladora4714.155