Research Article
Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast
Table 4
Results of simulation models in regard to total costs.
| Hydroelectric project | Budget at Completion (BAC) | Probability of cost equal to or less than BAC | Estimated cost for 95% probability | million US$ | | million US$ |
| Santiago | 2684 | 26.1 | 2839.2 | Cardenillo | 944 | 26.6 | 999.1 | Mazar Dudas | 56 | 21.6 | 59.29 | Sopladora | 678 | 22.7 | 714.4 |
|
|