Research Article

Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast

Table 5

Accuracy probability rates in cost forecasts (EVM) and duration forecasts (ES) for the Santiago project.

Analysis periodEarned Value (EV)Cost Accuracy Probability (%)Duration Accuracy Probability (%)
monthsmillionsProb. 95%range 2%  ± 26.8 millionrange 5%  ± 1.7 months

5299.0023.0023.20
10685.7028.3031.80
151204.9038.9032.10
201613.9043.2036.10
251859.9055.6037.70
302055.7072.0040.10
352215.6086.2042.40
402356.2096.2045.30
452476.6099.5046.30
502528.90100.0047.30
552570.30100.0054.60
602607.10100.0061.80
652653.00100.0052.00
682678.00100.0052.10
Completion2684.32100.00100.00