Research Article

Assessing the Impact of Virtual Standby Systems in Failure Propagation for Complex Wastewater Treatment Processes

Table 5

Simulation results-VSB scenario.

Equipment/systemPerformance indicators
Mean % availabilityMean % oper. timeMean processed WW (MGD)MTTF (hours)MTTR (hours)

Primary treatment process86.6289.728.0811.131.72
Standby bar screening197.2489.728.0893.443.53
BS_00196.6889.727.9745.881.4
BS_002226.9789.720.110.481.3
Standby grit chamber196.4389.728.0876.633.29
GRIT_00196.1989.727.9968.862.4
GRIT_00221.1589.720.090.592.2
PUMP_00195.7689.728.0828.751.2
CLAR_00296.4789.728.0898.423.2

1Two new subsystems (standby configuration) are recognized, representing the integration of the main and virtual equipment. The creation of these new subsystems is needed according to evaluation of the resilience operational impact over the indicators of interest. 2This virtual equipment approaches the impact of resilience condition on the main system and subsystems.