Production Decision Optimization for Iron and Steel Scrap Remanufacturing considering Carbon Emission and Delivery Time
Table 2
Multiobjective decision-making scheme.
| Scheme | Corresponding processing sequence | Delivery time (minutes) | Carbon emissions (ton) |
| 1 | 10 13 11 4 9 12 3 18 16 8 6 7 15 5 17 1 2 19 14 20 | 2042 | 2106 | 2 | 10 13 11 4 9 12 17 1 2 5 8 6 7 15 19 3 18 16 14 20 | 2043 | 2050 | 3 | 10 13 11 4 9 12 17 1 2 19 3 18 5 8 6 7 15 16 14 20 | 2046 | 2015 | 4 | 10 20 14 13 11 4 9 12 2 19 3 17 1 18 5 8 6 7 15 16 | 2050 | 1981 | 5 | 10 13 11 4 12 17 1 18 9 3 2 19 5 8 6 7 15 16 14 20 | 2071 | 1968 | 6 | 10 1 2 19 3 13 11 4 9 12 17 18 5 8 6 7 15 16 14 20 | 2082 | 1954 | 7 | 10 17 1 2 19 14 20 13 11 4 9 12 3 18 5 8 6 7 15 16 | 2090 | 1930 | 8 | 10 13 18 17 1 2 19 3 11 4 9 12 5 8 6 7 15 16 14 20 | 2100 | 1918 | 9 | 10 17 1 9 12 2 19 3 11 4 20 14 13 18 5 8 6 7 15 16 | 2107 | 1913 | 10 | 10 1 2 19 3 16 14 13 11 4 9 12 17 18 5 8 6 7 15 20 | 2126 | 1892 |
|
|