Production Decision Optimization for Iron and Steel Scrap Remanufacturing considering Carbon Emission and Delivery Time

Table 2

Multiobjective decision-making scheme.

SchemeCorresponding processing sequenceDelivery time (minutes)Carbon emissions (ton)

110 13 11 4 9 12 3 18 16 8 6 7 15 5 17 1 2 19 14 2020422106
210 13 11 4 9 12 17 1 2 5 8 6 7 15 19 3 18 16 14 2020432050
310 13 11 4 9 12 17 1 2 19 3 18 5 8 6 7 15 16 14 2020462015
410 20 14 13 11 4 9 12 2 19 3 17 1 18 5 8 6 7 15 1620501981
510 13 11 4 12 17 1 18 9 3 2 19 5 8 6 7 15 16 14 2020711968
610 1 2 19 3 13 11 4 9 12 17 18 5 8 6 7 15 16 14 2020821954
710 17 1 2 19 14 20 13 11 4 9 12 3 18 5 8 6 7 15 1620901930
810 13 18 17 1 2 19 3 11 4 9 12 5 8 6 7 15 16 14 2021001918
910 17 1 9 12 2 19 3 11 4 20 14 13 18 5 8 6 7 15 1621071913