Research Article
Developing an Integrative Data Intelligence Model for Construction Cost Estimation
Table 1
Descriptive measures of the cost data for the training phase.
| | Minimum | Maximum | Mean | Median | Std. deviation | Skewness | Kurtosis |
| Ground floor area (m2) | 200 | 5320 | 1622 | 1370 | 1196.252 | 1.127 | 0.466 | Total floor area (m2) | 355 | 9088 | 3135 | 2525 | 2214.788 | 1.079 | 0.466 | Floor number | 1 | 6 | 2.762 | 2 | 1.711 | 0.651 | −1.052 | Elevator number | 0 | 4 | 0.794 | 0 | 1.002 | 1.073 | 0.349 | Footing type (raft = 1; separated = 2) | — | — | — | — | — | — | — | Inflation (%) | 0.1 | 7.5 | 2.484 | 1.8 | 2.161 | 0.775 | −0.656 | Duration (days) | 122 | 731 | 357.6 | 348 | 137.171 | 0.715 | 0.652 | Cost ($) | 26756 | 6451519 | 1975260 | 1321630 | 1623076 | 0.903 | −0.312 |
|
|