Robust Proactive Project Scheduling Model for the Stochastic Discrete Time/Cost Trade-Off Problem

Table 2

Parameter settings.

Parameters Value

Number of activities 10; 20; 30
Order strength (OS)0.3; 0.5; 0.7
Number of modes 4; 8
Most likely activity durationUniformly drawn from 1, 50
Most likely smallest activity costUniformly drawn from 1, 10
Activity cost slopeUniformly drawn from 1, 8
Uniformly drawn from 0.1, 1
0.5