Table 2
The detailed indication of the letters A–T in Figures
5 and
6.
| A–E | Indication | F–J | Indication | K–O | Indication | P–T | Indication |
| A | Warehouse for used machine tool | F | Inspection center | K | Chromium electroplating | P | Polishing machine | B | Workshop office | G | Manually scraping center | L | Groove machine | Q | Gear hobbing machine | C | Warehouse for remanufactured machine tool | H | Rough grinding machine | M | Laser cladding | R | Lathe machine | D | Manually disassembly center | I | Cold welding machine | N | Press and straighten | S | Reassembly center | E | Automatic cleaning machine | J | Precision grinding machine | O | Planer machine | T | Unoccupied department |
|
|